Lead service: Cladding remediation and recladding, safely and to programme

We replace the outer wall of existing buildings: to remove unsafe materials, improve thermal performance or renew a tired elevation. Our teams handle strip-out, framing, fire barriers and new cladding as one package, with in-house design. We work as a specialist subcontractor to the main contractor.

Project capacity
Up to £50m
Approved fire stopping installer
FIRAS
Certified health and safety system
ISO 45001
Brick-slip cladding stepping up the elevation as it goes on, with scissor lifts behind the site barriers
Ark Oval Primary Academy, Croydon: GeBrik brick-slip cladding and aluminium flashings and copings for the school's renovation.

Why buildings are reclad

  • Fire safety

    Replacing combustible cladding and insulation, and installing cavity barriers and fire stopping to the fire strategy.

  • Old pebble-dashed concrete wall, new mineral wool insulation slabs fixed over it, and smooth pale grey façade panels finished beside them (illustrative image)

    Energy performance

    A new façade can add insulation and reduce heat loss through the walls.

  • Weathered precast concrete cladding with rust streaks from corroding fixings, cracked joints and water staining beside an old window (illustrative image)

    Condition

    Replacing deteriorating materials that leak, fail or pose a hazard to occupants and passers-by.

  • Copper-coloured aluminium panel rainscreen on Core 3, the stair core of Spelthorne Leisure Centre, beside a timber batten screen

    Appearance

    Giving an older building a new, modern elevation.

    Pictured: aluminium panel rainscreen on Core 3 at Spelthorne Leisure Centre, delivered by Express Facades.

What our recladding package covers

Strip-out, framing, boards, insulation, cavity barriers and new cladding can all sit in one package with us.

  • Survey support and review of the existing wall build-up
  • Careful strip-out of existing cladding, insulation and boards
  • New or repaired SFS
  • Sheathing boards, insulation and cavity barriers (see cavity barrier installation)
  • New cladding: rainscreen, fibre cement, brick slip, HPL, metal, render systems
  • Fire stopping by FIRAS-approved installers (see fire stopping)
  • Aluminium flashings and copings
Cladding systems we install
From strip-out to new façadeOne package
  1. Strip-outExisting cladding, insulation and boards
  2. SFSNew or repaired
  3. Sheathing boards and insulation
  4. Cavity barriers and fire stoppingTo the fire strategy
  5. New claddingRainscreen, fibre cement, brick slip, HPL, metal or render
  6. Flashings and copingsAluminium

Working on occupied and existing buildings

Recladding often happens around people who live, study or work in the building. We plan access, sequencing and protection with the main contractor so that each elevation is opened up, made safe and closed again in a controlled order.

Our site supervisors are SMSTS-trained and our operatives hold CSCS, IPAF and PASMA cards.

Aerial view of the new St Dunstan's College teaching block beside the Victorian college building in Catford
St Dunstan's College, Catford, for Willmott Dixon: the new block beside the Victorian college building.

How cladding remediation is procured

If you are planning remediation of an existing block, this is how the funded route works today. It summarises government guidance; it is not legal advice.

  • The pressure to act. The government's Remediation Acceleration Plan aims for every building of 18m or more in a government-funded scheme to be remediated by the end of 2029, with 11 to 18m buildings expected to finish by 2031. A Bill introduced on 14 October 2026 would put a legal duty on the responsible entity to assess and remediate buildings over 11m.
  • The scale. At the end of September 2026, 45% of the 4,732 monitored residential buildings of 11m or more with unsafe cladding had not started works, and only 30% of the 1,524 buildings eligible for the Cladding Safety Scheme had started. In April 2026, 1,078 London buildings in government schemes had yet to start, more than all other regions of England combined.
  • Who appoints whom. Under the Cladding Safety Scheme the grant agreement is with the responsible entity, the works are tendered before the works package is submitted, and the main contractor must be appointed principal contractor under CDM 2015. A PAS 9980 appraisal of the external walls comes first.
  • Higher-risk buildings. On a building of 18m or more, or seven or more storeys, with at least two homes, remediation is Category A building work: the Building Safety Regulator must approve it before work starts, and has up to eight weeks to decide for an existing building. Contractors gather the information that updates the building's golden thread.
  • Where we fit. We work as a specialist subcontractor to the main contractor, taking the external wall package: strip-out, framing, boards, insulation, cavity barriers, fire stopping and new cladding.

Sources: MHCLG building safety remediation data (September 2026), Greater London Authority (June 2026), Remediation Acceleration Plan (July 2025), Cladding Safety Scheme guidance (October 2026), building control for higher-risk buildings.

Recladding experience

Key facts and our scope for each package.

View all recladding projects
Adur Civic Centre after recladding in copper-coloured panels with new glazing

Commercial · 2019

Complete

Adur Civic Centre

Main contractor
Willmott Dixon
Location
Shoreham-by-Sea
  • SFS
  • CP board
  • GeBrik cladding
  • Trespa cladding
Aerial view of Cobham Free School: a cream rendered block with the school sign, above a brick base

Education · 2020

Complete

Cobham Free School, Phase 2

Location
Cobham
  • Strip-out
  • SFS
  • CP board
  • Flashings
  • +6 more: GeBrik cladding, render, ceilings, partitions, acoustic panels, fire stopping
Brick-slip cladding stepping up the elevation as it goes on, with scissor lifts behind the site barriers.

Education · 2017

Complete

Ark Oval Primary Academy

Location
Croydon
  • GeBrik cladding
  • Flashings

Tenders and estimates

Planning a recladding project?

Send us the existing drawings, surveys and the new specification. We will review the scope and price it as one package.

What do you need?

Please enter your name.

Please enter your company.

Please enter a valid email address.

Please enter the project name.

What should we price? (tick all that apply)

Please choose at least one package, or "Not sure yet".

Drawings (needed for an estimate)

    Please attach the drawings for your estimate.

    Please confirm you have read the privacy notice.

    Recladding questions

    Anything else? Call 01708 554777.

    Can you reclad a building while it is occupied?

    Yes, with the right planning. We agree access, sequencing and protection with the main contractor so that each elevation is opened and closed in a controlled order.

    Do you remove the existing cladding as well as install the new?

    Yes. Strip-out, framing, boards, insulation, cavity barriers and new cladding can all sit in one package with us.

    Do you install cavity barriers and fire stopping?

    Yes. We are a FIRAS-approved installer of fire stopping, and cavity barriers form part of our façade and recladding packages. See cavity barrier installation.

    Can you replace or repair the SFS behind the cladding?

    Yes. We supply and install SFS and can replace or extend framing where the existing structure needs it. The MET-PRO SFS and Express ALU Pro rainscreen we install come from our sister company, Express Facades.

    What size of recladding package can you take on?

    We have the capacity to deliver façade, recladding and drylining packages on projects worth up to £50m.

    Who appoints the contractor on a Cladding Safety Scheme project?

    The responsible entity holds the grant agreement and tenders the works, and the main contractor must be appointed principal contractor under CDM 2015. As a specialist, we work for the main contractor on the external wall package.

    Does remediation of a high-rise building need approval before work starts?

    On a higher-risk building (18m or more, or seven or more storeys, with at least two homes), yes: remediation is Category A building work, and the Building Safety Regulator must approve it before work starts. It has up to eight weeks to decide for an existing building.

    Computer-generated illustrations and renders, not photographs of our projects.